Capital Improvement Program
Cavanaugh Road 24” By-Pass Water Main
May 2020
The first pre-engineered, factory tested and fully operable PRV Chamber to be
utilized by the MVWA. This new chamber was installed to replace a very small
manhole type chamber with inoperable valves. The work was accomplished in
several days as opposed to several weeks if constructed on site. The station
was in service one day after final connections were made.
Excavation at Pond Lane & Albany Street.
Rig-All setting the Chamber.
Connections to existing Main in Albany Street.
New 6” & 2” PRV and Isolating Valves.