Capital Improvement Program

Cavanaugh Road 24” By-Pass Water Main

May 2020

The first pre-engineered, factory tested and fully operable PRV Chamber to be utilized by the MVWA. This new chamber was installed to replace a very small manhole type chamber with inoperable valves. The work was accomplished in several days as opposed to several weeks if constructed on site. The station was in service one day after final connections were made.


man in excavator clearing work area

Excavation at Pond Lane & Albany Street.

 crane setting the PRV chamber in ground

Rig-All setting the Chamber.

connected exisiting pipes to the chamber inside of pit

Connections to existing Main in Albany Street.

in the pit, man outside the chamber with open view of valves inside chamber

New 6” & 2” PRV and Isolating Valves.