Southern Reservoir FEMA Damage Repairs Project
Completed July 2022
Work included remediation of 2019 Halloween Storm damage at four locations
surrounding Reservoir No. 2. Project scope consisted primarily of erosion repairs
with new rip-rap at bypass channel, placement of a new concrete overflow spillway
and stone abutment repair at the spillway bridge, reservoir bank failure repairs,
stone drainage channel lining, and general site restoration.