Capital Projects Committee Report
July 16, 2007
Capital Projects Committee:
A Capital Projects Committee meeting is scheduled for July 12, 2007 at Noon. Tentative agenda items include:
IDSE Contract Increase, Phase 2 Hydraulic Model Contract Decrease.
In-Line Hydro Generation Study. NYSERDA Grant MVWA Funding Share.
Construction Engineering Submittal Review Authorization for WTP Clearwell & Deerfield Tank.
Capital Projects Update:
In general, construction activities have accelerated on both major Tank projects and the Engineering Department staff and consultants are closely monitoring the progress on these and other projects noted below:
WTP Clearwell: Blasting of 13,000 tons of rock is complete. Casting bed have been prepared. Contractor is installing connecting 48 diameter piping to the tank foundation area.
Canal Crossing
MVWA is beginning design of replacement of transmission main valves on south
side of
Marcy Reservoir Tank
& Toby Road Tanks: Part
1, Environmental Assessment Form (EAF) has been issued to Involved &
Interested Agency comments. Some comments have been received. Site survey is nearly complete. Purchase offer for
Initial Distribution System Evaluation (IDSE): Hydraulic Model team beginning work and GIS/mapping updates are nearing completion. MVWA staff is providing key system data on pumps, valves, tanks, etc. for model input.
Smith Hill Tank: Site survey has been completed, base mapping in preparation.