CIP (6) Month Bid Schedule 07-16-07


Project Start Date: Mon 6/12/06
Project Finish Date: Thu 11/1/07

Tasks

ID
Task Name
Start Finish
1
Commence Field Survey for New Marcy Reservoir Tank site.
Mon 6/11/07Mon 6/11/07
2
Complete Field Survey for New Marcy Reservoir Tank.
Wed 8/1/07Wed 8/1/07
3
RCP - Deerfield Reservoir Complete Floor Slab, Start Dome Falsework.
Wed 6/27/07Wed 6/27/07
4
RCP - Deerfield Reservoir Wall Construction.
Mon 7/16/07Mon 7/16/07
5
RCP - Complete Blasting @ WTP. Begin Casting.
Wed 6/27/07Wed 6/27/07
6
Water Mains - Commence Construction of Holland Patent Borings. (Hold Per NYSDOT.)
Mon 8/13/07Mon 8/13/07
7
RCP - Pre-Construction Meeting for WTP Clearwell.
Mon 5/7/07Mon 5/7/07
8
IDSE - EPA has approved IDSE. Modeling is underway.
Wed 5/9/07Wed 5/9/07
9
Commence Design of Replacement Valves at South Side Canal Crossing.
Mon 7/2/07Mon 7/2/07
10
Complete Field Survey of New Smith Hill Tank site.
Mon 7/2/07Mon 7/2/07
11
Water Mains - Finish all Holland Patent Connections.
Mon 9/17/07Mon 9/17/07
12
RCP - Deerfield Reservoir Tank - Complete Wall Panels and Erection.
Mon 9/3/07Mon 9/3/07
13
RCP - WTP Clearwell - Complete Wall Erection.
Mon 9/3/07Mon 9/3/07
14
RCP - Deerfield Reservoir Tank Complete and Test Tank.
Mon 10/1/07Mon 10/1/07
15
RCP - WTP Clearwell Complete and Test Tank.
Thu 11/1/07Thu 11/1/07

Back