Project Start Date: Mon 6/12/06
Project Finish Date: Thu 11/1/07
| ID |
Task Name | Start | Finish |
|---|---|---|---|
| 1 | Commence Field Survey for New Marcy Reservoir Tank site. |
Mon 6/11/07 | Mon 6/11/07 |
| 2 | Complete Field Survey for New Marcy Reservoir Tank. |
Wed 8/1/07 | Wed 8/1/07 |
| 3 | RCP - Deerfield Reservoir Complete Floor Slab, Start Dome Falsework. |
Wed 6/27/07 | Wed 6/27/07 |
| 4 | RCP - Deerfield Reservoir Wall Construction. |
Mon 7/16/07 | Mon 7/16/07 |
| 5 | RCP - Complete Blasting @ WTP. Begin Casting. |
Wed 6/27/07 | Wed 6/27/07 |
| 6 | Water Mains - Commence Construction of Holland Patent Borings. (Hold Per NYSDOT.) |
Mon 8/13/07 | Mon 8/13/07 |
| 7 | RCP - Pre-Construction Meeting for WTP Clearwell. |
Mon 5/7/07 | Mon 5/7/07 |
| 8 | IDSE - EPA has approved IDSE. Modeling is underway. |
Wed 5/9/07 | Wed 5/9/07 |
| 9 | Commence Design of Replacement Valves at South Side Canal Crossing. |
Mon 7/2/07 | Mon 7/2/07 |
| 10 | Complete Field Survey of New Smith Hill Tank site. |
Mon 7/2/07 | Mon 7/2/07 |
| 11 | Water Mains - Finish all Holland Patent Connections. |
Mon 9/17/07 | Mon 9/17/07 |
| 12 | RCP - Deerfield Reservoir Tank - Complete Wall Panels and Erection. |
Mon 9/3/07 | Mon 9/3/07 |
| 13 | RCP - WTP Clearwell - Complete Wall Erection. |
Mon 9/3/07 | Mon 9/3/07 |
| 14 | RCP - Deerfield Reservoir Tank Complete and Test Tank. |
Mon 10/1/07 | Mon 10/1/07 |
| 15 | RCP - WTP Clearwell Complete and Test Tank. |
Thu 11/1/07 | Thu 11/1/07 |