CIP (6) Month Bid Schedule 03-26-07


Project Start:
Project Finish:
Mon 6/12/06
Wed 8/1/07

Tasks

ID
Task Name
StartFinish
1
Begin Survey & Design of FY 08 MVWA Main Projects.
Mon 4/2/07Mon 4/2/07
2
Commence Field Survey for New Marcy and Toby Road Tanks.
Fri 6/1/07Fri 6/1/07
3
Complete Field Survey for New Marcy and Toby Road Tanks.
Wed 8/1/07Wed 8/1/07
4
RCP - Issue RFP/Q for Construction Observation @ Deerfield & WTP.
Tue 2/27/07Tue 2/27/07
5
RCP - Final WTP Clearwell Plans - Bidding.
Mon 4/2/07Mon 4/2/07
6
RCP - Award Construction Contracts @ Deerfield.
Mon 3/26/07Mon 3/26/07
7
RCP - Award Construction Observation @ Deerfield & WTP.
Mon 3/26/07Mon 3/26/07
8
RCP - Commence Construction at Deerfield.
Mon 4/16/07Mon 4/16/07
9
CIP - Award Construction of Holland Patent Boring under Route 365.
Mon 2/26/07Mon 2/26/07
10
RCP - Close SEQR for Marcy Reservoir Tank
Mon 7/2/07Mon 7/2/07
11
RCP - Award Construction Contracts @ WTP.
Mon 4/16/07Mon 4/16/07
12
RCP - Commence Construction @ WTP.
Mon 5/14/07Mon 5/14/07
13
Water Mains - Commence Construction of Holland Patent Borings
Tue 5/1/07Tue 5/1/07