CIP (6) Month Bid Schedule 02-26-07

Project Start:
Project Finish:
Mon 6/12/06
Wed 8/1/07

Tasks

ID
Task Name
StartFinish
1
Begin Survey & Design of FY 08 MVWA Main Projects.
Mon 4/2/07Mon 4/2/07
2
Commence Field Survey for New Marcy and Toby Road Tanks.
Fri 6/1/07Fri 6/1/07
3
Complete Field Survey for New Marcy and Toby Road Tanks.
Wed 8/1/07Wed 8/1/07
4
RCP - Complete WTP Clearwell Soils Investigation.
Fri 2/16/07Fri 2/16/07
5
RCP - Preliminary Deerfield Tank Plans for MVWA & DOH Review.
Tue 1/16/07Tue 1/16/07
6
RCP - Final Deerfield Tank Plans - Bidding.
Fri 2/2/07Fri 2/2/07
7
RCP - Issue SEQR EAF for Marcy Reservoir Tank.
Wed 3/21/07Wed 3/21/07
8
RCP - Issue RFP/Q for Construction Observation @ Deerfield & WTP.
Tue 2/27/07Tue 2/27/07
9
RCP - Final WTP Clearwell Plans - Bidding.
Fri 3/2/07Fri 3/2/07
10
RCP - Award Construction Contracts @ Deerfield.
Tue 3/20/07Tue 3/20/07
11
RCP - Award Construction Observation @ Deerfield & WTP.
Mon 3/19/07Mon 3/19/07
12
RCP - Commence Construction at Deerfield.
Mon 4/16/07Mon 4/16/07
13
CIP - Award Construction of Holland Patent Boring under Route 365.
Mon 2/26/07Mon 2/26/07
14
RCP - Close SEQR for Marcy Reservoir Tank
Mon 7/2/07Mon 7/2/07
15
RCP - Award Construction Contracts @ WTP.
Mon 4/16/07Mon 4/16/07
16
RCP - Commence Construction @ WTP.
Mon 5/14/07Mon 5/14/07

Back