| ID | Task Name | Start | Finish |
| 1 | Begin Survey & Design of FY 08 MVWA Main Projects. | Mon 4/2/07 | Mon 4/2/07 |
| 2 | Commence Field Survey for New Marcy and Toby Road Tanks. | Fri 6/1/07 | Fri 6/1/07 |
| 3 | Complete Field Survey for New Marcy and Toby Road Tanks. | Wed 8/1/07 | Wed 8/1/07 |
| 4 | RCP - Complete WTP Clearwell Soils Investigation. | Fri 2/16/07 | Fri 2/16/07 |
| 5 | RCP - Preliminary Deerfield Tank Plans for MVWA & DOH Review. | Tue 1/16/07 | Tue 1/16/07 |
| 6 | RCP - Final Deerfield Tank Plans - Bidding. | Fri 2/2/07 | Fri 2/2/07 |
| 7 | RCP - Issue SEQR EAF for Marcy Reservoir Tank. | Wed 3/21/07 | Wed 3/21/07 |
| 8 | RCP - Issue RFP/Q for Construction Observation @ Deerfield & WTP. | Tue 2/27/07 | Tue 2/27/07 |
| 9 | RCP - Final WTP Clearwell Plans - Bidding. | Fri 3/2/07 | Fri 3/2/07 |
| 10 | RCP - Award Construction Contracts @ Deerfield. | Tue 3/20/07 | Tue 3/20/07 |
| 11 | RCP - Award Construction Observation @ Deerfield & WTP. | Mon 3/19/07 | Mon 3/19/07 |
| 12 | RCP - Commence Construction at Deerfield. | Mon 4/16/07 | Mon 4/16/07 |
| 13 | CIP - Award Construction of Holland Patent Boring under Route 365. | Mon 2/26/07 | Mon 2/26/07 |
| 14 | RCP - Close SEQR for Marcy Reservoir Tank | Mon 7/2/07 | Mon 7/2/07 |
| 15 | RCP - Award Construction Contracts @ WTP. | Mon 4/16/07 | Mon 4/16/07 |
| 16 | RCP - Commence Construction @ WTP. | Mon 5/14/07 | Mon 5/14/07 |